The draft 'Ordinance to Amend Certain Nepal Acts Relating to Investment and Infrastructure, 2083' prepared by the government proposes provisions including protecting public officials' good-faith decisions from corruption charges, concluding fast-track arbitration in commercial disputes within 120 days, and requiring at least 50 percent physical progress for IPOs of hydropower projects under construction. It is noted that this is still only a draft and the government has not yet decided whether to bring it through an ordinance or present it as a bill in Parliament.
The draft 'Ordinance to Amend Certain Nepal Acts Relating to Investment and Infrastructure, 2083' prepared by the government proposes that a corruption offense shall not be established merely on the ground that a public official's good-faith decision had a minor error or did not produce the expected result.
The draft proposes provisions including fast-track arbitration in commercial disputes, timelines for mediation of commercial disputes, a one-stop system for forest area use for mining and infrastructure projects, and a requirement of at least 50 percent physical progress for IPOs of hydropower projects under construction.
This is still only a draft. The government has not yet decided whether to bring it through an ordinance or present it as a bill in Parliament.
Corruption Prevention Act: Protection for Good-Faith Decisions
According to the draft, an explanation will be added to Section 8 of the Corruption Prevention Act, 2059. Accordingly, the elements of a corruption offense shall not be deemed fulfilled merely due to ordinary administrative or technical errors in public work or contract implementation, differences in professional or technical opinion, or failure to achieve the expected result.
It is proposed that a conclusion of bad intent should not be drawn solely on the basis of information received after the decision or the fact that the expected result was not achieved. However, the draft states that investigation and action shall not be obstructed if it is proven that facts or evidence were knowingly concealed, falsely presented, or that there was an intent to provide unlawful benefit while making the decision.
It is proposed that the overall examination of cause and evidence be conducted for delays in decisions during implementation of public construction or procurement contracts due to technical complexities, design changes, or natural disasters. However, there is no proposal to grant immunity to acts of reducing quality or quantity with dishonest intent in construction and supply.
Arbitration and Mediation: Timelines to Be Set
Institutional and Fast-Track Arbitration
A provision for institutional arbitration will be added to the Arbitration Act, 2055. Recognition from the government will be required to operate an arbitration institution, and the government must grant recognition or reject with reasons within 60 days of receiving an application with full details.
In fast-track arbitration adopted with the written consent of the parties, the arbitrator must render a decision within 120 days. If there are reasonable grounds, the deadline may be extended once by up to 60 days, and thereafter by up to 90 days with the written consent of the parties.
Mediation of Commercial Disputes in 30 Days
It is proposed to amend the Mediation Act, 2068 to require completion of the mediation process for commercial disputes within 30 days of its commencement. If no agreement is reached, the process may continue for an additional 30 days with the written consent of the parties. A provision allowing mediation through electronic means is also proposed.
The draft also aims to amend the Insolvency Act, 2063 to simplify the insolvency and restructuring process for small and medium companies.
Hydropower IPOs: Condition of 50 Percent Progress
The draft proposes amending the Securities Act to allow hydropower companies under construction to issue IPOs to the general public only after achieving at least 50 percent physical progress. There is also a proposal that such companies' IPO applications shall not be rejected solely on the ground that commercial production has not yet started.
It is proposed that the project's physical progress must be certified by an independent and qualified technical evaluator, total cost, remaining work, additional investment requirements, and confirmed financial sources must be disclosed, and the amount raised from the IPO must be spent for the purpose of the approved project itself.
Mining, Forests, and Environment
It is proposed to amend the Mines and Minerals Act, 2042 to allow applications for forest area use through a one-stop system via the Department of Mines and Geology. However, the draft states that obtaining permission to operate a mine shall not automatically confer the right to use national forests or fell trees, and the final decision on forest area use shall be made by the authorized forest body.
It is proposed to amend the Forest Act, 2076 to require the Divisional Forest Office to publish the estimated annual quantity of forest produce that can be collected and sold by within Ashoj each year. A provision is also proposed allowing community forest user groups to enter into supply agreements with industries for a fixed period and to operate forest-based enterprises.
A provision is proposed in the Environment Protection Act, 2076 for an integrated electronic service for environmental approval and monitoring based on risk.